The stages

The RIBA Plan of Work stages, explained for owners

A building project in 8 stages, and what you sign off at the end of each.

A pencil and scale rule on a construction drawing

The RIBA Plan of Work splits a building project into 8 stages, numbered 0 to 7, from deciding whether to build at all to running the finished building. It’s published by the Royal Institute of British Architects in the UK, and this guide follows its 2020 edition. It isn’t a law or a contract. It’s a shared map that owners, consultants and contractors can all work to, wherever the project is.

Lockd’s own process, the Lockd Method, is aligned with it, and every stage ends with your sign-off before the next one starts. Here’s what happens in each stage, and what you’re asked to sign off.

Stage Name In one line
0 Strategic Definition Should you build at all?
1 Preparation and Briefing What you want, written down as a brief
2 Concept Design The first design, with a cost plan
3 Spatial Coordination The architecture and the engineering made to fit
4 Technical Design Everything needed to build
5 Manufacturing and Construction Building it, up to Practical Completion
6 Handover Handover and the defects period
7 Use The life of the building

Stage 0: Strategic Definition

Nothing is designed yet. The question is whether a building project is the right answer to your need.

  • Your requirements are written down.
  • A business case compares the options, with their risks and budgets.
  • Possible sites are appraised.

What you sign off: your requirements, and the decision to go ahead. Changes cost least now, before anything is drawn. More in Stage 0: should you build at all?

Stage 1: Preparation and Briefing

Stage 1 turns what you want into a brief the whole team can work to. The team prepares:

  • the Project Brief: outcomes, quality, space needs and sustainability
  • feasibility studies and site surveys
  • the budget and the programme
  • how the project will be procured, and who is responsible for what

What you sign off: a Project Brief that fits your site and your budget. Set the budget first: the budget comes before the brief.

Stage 2: Concept Design

Stage 2 is the first design: the concept.

  • The architect develops the concept with engineering input.
  • A cost plan and an outline specification are prepared.
  • Strategies are set for fire safety, sustainability, health and safety, and inclusive design.

What you sign off: a concept that meets your brief. Anything that departs from the brief is listed for you to accept or reject. Ask to see the cost plan against your budget before you sign off the look: the renders aren’t the budget.

Stage 3: Spatial Coordination

Stage 3 is where the architecture and the engineering are made to fit together.

  • Design studies and engineering analysis coordinate the design.
  • Costs are checked against the plan.
  • Change control starts: from here, every change is logged with its cost and time.

What you sign off: a design that’s coordinated across the architect and the engineers. Make the big decisions before you sign off Stage 3, because changes cost more from here on.

Stage 4: Technical Design

Stage 4 produces everything needed to build.

  • The design team and specialist subcontractors complete the technical design.
  • The final specifications are written.
  • The consultants complete their submissions to the authorities.
  • On a traditional route, the contractor is tendered and appointed.

What you sign off: complete information to build from. Stages 4 and 5 often overlap. That’s normal, as long as the key approvals are in before site work starts. Why a finished design matters: finish the design before you tender.

Stage 5: Manufacturing and Construction

Stage 5 runs from the day the contractor takes the site to Practical Completion.

  • The building goes up, with progress and quality checks.
  • Site queries are answered and changes are controlled.
  • Systems are tested and commissioned.
  • The Building Manual is put together.

What you sign off: Practical Completion, with the list of defects still to fix. Don’t accept Practical Completion without the defects list attached. While it’s being built: inspect before it’s covered, and remember that every change has a price and a date.

Stage 6: Handover

Stage 6 starts at handover and ends with the Final Certificate.

  • The building is handed over and goes into use.
  • Defects are fixed through the defects liability period.
  • Systems are fine-tuned across the seasons.
  • The team reviews how the building performs.

What you sign off: the Final Certificate, at the end of the defects liability period. Put the end of the defects period in your diary, and report defects before it ends. Before you accept the building: agree the snag list before you take the keys.

Stage 7: Use

Stage 7 lasts as long as your building does.

  • The building is run and maintained.
  • A post-occupancy evaluation checks it against the original brief.
  • The Building Manual is kept up to date.

What you sign off: nothing. This stage runs for the life of the building. Keep the Building Manual current: it’s the first thing the next team will ask for.

When does the contractor join?

The RIBA Plan of Work doesn’t fix when the contractor arrives. Your procurement route does:

Route When the contractor usually joins
Traditional The design is finished first, and the contractor is tendered and appointed in Stage 4
Design and build, single stage Your requirements are fixed at the end of Stage 3, and the contractor is appointed at the start of Stage 4
Design and build, two stage Your requirements are fixed at the end of Stage 2; the contractor helps through Stage 3 under a pre-contract agreement, then is appointed at the start of Stage 4
Management contracting The contractor joins at Stage 2

Each route trades speed, cost certainty and risk differently. Choose it at Stage 1, on purpose.

How the Lockd Method lines up

Lockd Method step RIBA stages
Lock the brief 0–1
Onboard the right team 1–4
Control delivery 5
Keep you informed Every stage
Deliver the handover 6–7

Where Lockd comes in

As your Client Representative, we run each stage’s stop point for you: the stage’s documents collected, your sign-off asked for with the evidence attached, and nothing moving on until you’ve approved it. More in every stage ends with your sign-off.

Source: RIBA Plan of Work 2020, Royal Institute of British Architects. Stage names checked 18 October 2026.